Program & Construction Management

GE Transportation – GEMx Renewable Energy Battery Plant

Schenectady, NY (2011)

Established more than 100 years ago, GE Transportation is a division of General Electric Company and is a leading supplier of technology and products to the railroad, marine, drilling, mining, and wind industries.

MOCA Services: 

 

MOCA Services

  • On-site construction cost control management
  • Owner and contractor coordination and reporting
Homepage Promo Image: 
GEMx_1.jpg

Lake Erie Biofuels Plant

Erie, Pennsylvania (2007 - 2008)

Lake Erie Biofuels Plant is Pennsylvania's first large-scale biodiesel production facility and one of the five largest in the nation with annual production capacity of about 45 million gallons. It was built on land formerly owned by International Paper Co. at a cost of more than $50 million. As a supplier of alternative fuel additive methyl ester, the Lake Erie Biofuels Plant is a state-of-the-art biodiesel plant that meets new voluntary quality-assurance standards. Biodiesel is a fuel made from animal fats or vegetable oil.

MOCA Services: 

MOCA Services

  • Cost engineering with local economic market analysis
  • Detailed project scheduling
  • Construction simulation (MOCABuild)
  • Construction oversight
  • Progress audits, monitoring and payment control
  • Trending and recovery option identification
Homepage Promo Image: 
260h_LakeErie-1.jpg

Dover Air Force Base C-17 Air Freight Terminal

in
Dover, Delaware (2005-2008)

Dover Air Force Base is the active duty military host for the 436th Airlift Wing, consisting of over 4,000 active-duty military and civilian employees. To support the airlift mission of the C-17 Globemaster III aircraft at Dover AFB, the US Air Force invested hundreds of millions of dollars in new hangars, infrastructure, and aviation facilities. The base construction program included a new $77 million, 370,000 square foot C-17 Air Freight Terminal (AFT) that includes an oversized cargo facility and main building with maintenance and operational sections.

MOCA Services: 

MOCA Services

  • Programming
  • Project Controls
  • Cost Engineering
  • Scheduling
  • Construction Simulation (MOCABuild)
  • Construction Oversight and Monitoring
  • Change Order and Claims Assessments
Quote: 

“MOCA Systems provided the Air Force Air Mobility Command (AMC) and Dover Base CE (BCE) with their differentiated MOCABuild project controls system on the $77 million Air Freight Terminal / Oversized Cargo Facility at Dover AFB. By having a thorough and detailed understanding of the project costs, achievable schedule durations and labor resources required to complete the work, MOCA was able to identify to the AF where the project was at risk. This proactive approach allowed the AMC and BCE the ability to engage with the construction agent and contractor early in the project and to substantially reduce the claims and changes form the contractor”.

Chief of Military Construction, Base Civil Engineering, Dover AFB

Homepage Promo Image: 
260h_DoverairfreightterminalEdited.jpg